CONSTRUCTION UNIT PRICE FOR MAINTAINING AND REPAIRING
Updated : January, 2017
No. |
Item of works |
Unit |
Minimum |
Rate (VND) |
Remark |
1 |
Excavation by handwork |
m3 |
15 |
198,400 |
|
2 |
Disposal surplus soil |
m3 |
15 |
163,900 |
|
3 |
Driving Cajuput Piles |
tree |
50 |
34,400 |
1st grade, straight |
4 |
Lean concrete, Grade 100 |
m3 |
1 |
1,377,300 |
True aggregate and grade |
5 |
Small concrete structure, grade 250 |
m3 |
1 |
1,772,400 |
True aggregate and grade |
6 |
Ordinary concrete grade 250 |
m3 |
5 |
1,674,000 |
True aggregate and grade |
7 |
Concrete for slab floor, grade 200 |
m3 |
3 |
1575,600 |
True aggregate and grade |
8 |
Complicated formwork |
m2 |
10 |
196,800 |
|
9 |
Ordinary formwork |
m2 |
10 |
167,200 |
|
10 |
Supply and erection reinforced bar |
kg |
150 |
23,600 |
Steel Vinakyoei, Pomina |
11 |
Stone agg 0x4 (sub_base) leveling sub_grade |
m3 |
10 |
336,100 |
|
12 |
Sand leveling sub_grade |
m3 |
10 |
277,100 |
|
13 |
Solid brick for complicated structures |
m3 |
1 |
2,459,400 |
Tunnel furnace solid hollow brick |
14 |
100mm thick hollow brick wall |
m2 |
15 |
189,200 |
Tunnel furnace clay hollow brick |
15 |
100mm thick solid brick wall |
m2 |
15 |
297,400 |
Tunnel furnace solid hollow brick |
16 |
200mm thick hollow brick wall |
m2 |
10 |
331,600 |
Tunnel furnace clay hollow brick |
17 |
200mm thick solid brick wall |
m2 |
10 |
488,400 |
Tunnel furnace solid hollow brick |
18 |
Mortar plastering to finish surface of concrete |
m2 |
40 |
128,400 |
True aggregate and grade |
19 |
Mortar plastering to finish wall. |
m2 |
40 |
108,700 |
True aggregate and grade |
20 |
Supply and erection of steel purlin, rafter, batten |
kg |
100 |
27,500 |
Huu Lien Asia shape steel |
21 |
Tiling tiles on roof |
m2 |
50 |
255,800 |
Dong Tam brand |
22 |
Covering sheets on roof |
m2 |
50 |
167,200 |
Hoasen, Povina sheet metal |
23 |
Exposed gypsum ceiling |
m2 |
30 |
127,900 |
Vinh Tuong board and frame |
24 |
Moistbloc gypsum ceiling |
m2 |
30 |
177,100 |
Vinh Tuong board and frame |
25 |
Concealed gypsum ceiling |
m2 |
30 |
157,400 |
Vinh Tuong board and frame |
26 |
Drywall - 1 side |
m2 |
15 |
236,100 |
Vinh Tuong board and frame |
27 |
Drywall - 2 sides |
m2 |
15 |
275,500 |
Vinh Tuong board and frame |
28 |
Putty ordinary mastic on wall |
m2 |
60 |
34,400 |
Joton skimcoat (putty powder) |
29 |
Putty highquality mastic on wall |
m2 |
60 |
41,300 |
Putty powder ICI Cemputty |
30 |
Painting emulsion outdoor - ICI exterior Maxillte |
m2 |
60 |
41,300 |
Emulsion paints ICI - Maxilitte |
31 |
Painting emulsion outdoor - Jotun exterior paints |
m2 |
60 |
63,900 |
Emulsion paints Jotun - Strax |
32 |
Painting emulsion outdoor - ICI Dulux Wea. |
m2 |
60 |
66,900 |
Emulsion paints ICI - Dulux Wea.Shield |
33 |
Painting emulsion indoor - ICI interior Maxillte |
m2 |
60 |
35,400 |
Emulsion paints ICI - Maxilitte |
34 |
Painting emulsion indoor - Jotun interior paints |
m2 |
60 |
44,300 |
Emulsion paints Jotun - Jota |
35 |
Painting emulsion indoor - ICI Dulux Wea. |
m2 |
60 |
51,200 |
Emulsion paints ICI - Dulux Wea.Shield |
36 |
Waterproof according technological process |
m2 |
15 |
177,100 |
Sika technology |
37 |
Tiling tiles on floor, wall |
m2 |
30 |
315,500 |
Tile price under 200.000VND/m2 |
38 |
Aluminium glass door, window - Hondalex, Xingfa brand |
m2 |
5 |
1,823,200 |
8mm thick glass, aluminium frame, 2mm thick |
39 |
Hollow steel, 2mm thick. glass tempered door, window. |
m2 |
5 |
1,650,320 |
8mm thick tempered glass, Hollow steel frame |
40 |
Natural hard wood door |
m2 |
5 |
3,148,000 |
100% natural hard wood |
Contact information :
VAN TUONG ENGINEERING CONSTRUCTION J.S.C
Address : 211 Nguyen Trong Tuyen st., ward 8, Phu Nhuan dist., HCMC, VN
Telephone : 2218 2157 - Hotline : 0913 155 552
Email :
This e-mail address is being protected from spambots. You need JavaScript enabled to view it
– www.vantuong.vn